Construction Continues at Providence Medical Center...
The construction project is continuing nicely. In the new Oncology/Outpatient addition, painting and all of the vinyl flooring is nearly complete. Ceiling grid work is in place throughout this new space. The roof-top heating/cooling unit has been put in place. The 'break through' into the existing area has been done and remodel of this space nearly completed as well. The Wellness/Therapy addition to the southwest is progressing well. Painting has begun, along with the ceiling grid work being installed. Delivery of the pool for therapy is expected in the coming weeks. Overall, the project is around 70% to 80% complete.